The Town of Derry issued a competitive RFP (B24‑106) for trenchless rehabilitation of approximately 2,848 linear feet of 8‑inch sanitary sewer pipe using Cured‑In‑Place Pipe (CIPP) technology. Proposals were due by 2 pm on April 19, 2024, and the contract was awarded to Green Mountain Pipeline Service based on a unit‑price bid of roughly $99 k. The work includes pipe cleaning, CIPP installation, CCTV inspection, traffic control, and restoration of service connections, with completion preferred by June 28, 2024. Payment is net‑30 after final acceptance.
• Scope: CIPP liner (8″ × 4.75 mm or equivalent) for 8‑inch host sewer segments, full‑service turnkey delivery.
• Procurement: Full and open competition; award based on lowest unit‑price bid.
• Timeline: Bid deadline 19 Apr 2024; preferred work finish by 28 Jun 2024; net‑30 payment terms.