The contract is for asbestos abatement work in Keene Hall at Eastern Kentucky University. The work includes furnishing all labor, materials, equipment, and services necessary for the complete abatement. The contract has a substantial completion date of 90 days after receipt of the order and a final completion date of 105 days after receipt of the order. The contract also includes liquidated damages of $500 per day until substantial completion and $200 per day until final completion.
• The contract requires bidders to provide surety bonds.
• The contract requires bidders to provide a list of similar projects in both size and scope.
• The contract requires bidders to provide a list of current projects under contract and bonded.
• The contract requires bidders to upload a current ACORD certificate of insurance.
• The contract has a bid guaranty requirement.
• The contract has a payment term of Net 30.