The contract is for facilities ADA improvements at the South Texas Art Museum and Barge Dock Parking Lot. The project includes the construction of two ADA accessible routes, one from the South Texas Art Museum parking lot to the building's main entrance, and one from the Barge Dock parking lot to street level near the American Bank Center. The contract was awarded to JE Construction Services and Barcom Construction, with a total bid tabulation of $340,243.31. The contract includes various items such as mobilization, site clearing, site grading, and concrete work. The engineer's estimate for the project is $354,190.00.
The key features of the proposed base bid construction are: Concrete ADA Ramps, Powder Coated Aluminum Pedestrian Railing, Placement of Compacted Select Fill Material, Concrete Drilled Piers, Concrete Sidewalk, and Signing/Striping.
The contract also includes additive/alternate items such as aluminum ADA ramps and powder coated aluminum pedestrian railing, and concrete pavement repair and signing.
The contract was bid on by multiple vendors, with JE Construction Services and Barcom Construction being the two vendors awarded the contract.
The contract is for a public project, and the bid tabulation includes the unit costs and totals for each item.
The contract includes a pre-bid conference, which was held on March 4, 2014, at 10:30 AM.
The contract also includes a bid submission date, which was March 12, 2014, at 2:00 PM.
The contract is subject to the terms and conditions of the City of Corpus Christi, and the vendors must comply with all applicable laws and regulations.
Some of the other key points of the contract include:
• The contract is for a fixed price, with the total bid tabulation being $340,243.31.
• The contract includes a payment schedule, with payments being made based on the completion of certain items.
• The contract includes a warranty period, with the vendors being responsible for any defects or issues that arise during the warranty period.
• The contract includes a termination clause, with the City of Corpus Christi having the right to terminate the contract if the vendors fail to comply with the terms and conditions of the contract.
The contract is a significant investment for the City of Corpus Christi, and it is expected to have a positive impact on the community.
The contract is also expected to provide opportunities for local businesses and vendors, and to stimulate economic growth in the area.
Overall, the contract is an important step forward for the City of Corpus Christi, and it is expected to have a lasting impact on the community.