The City of Everett is seeking a contractor to repair a leaking 84-inch concrete-lined steel pipe at the Water Filtration Plant. The contractor will need to provide and install a WEKO-SEAL to secure the leak. The pipe is buried and only accessible via a reservoir located approximately 100 feet from the leaking joint. The budget estimate for this project is $27,000. The contract was awarded to Ballard Marine Construction Inc for a total of $27,887.25.
• The project involves repairing a leaking pipe at the Water Filtration Plant
• The contractor must provide and install a WEKO-SEAL to secure the leak
• The pipe is buried and only accessible via a reservoir
• The budget estimate for this project is $27,000
• The contract was awarded to Ballard Marine Construction Inc