The Avila Beach Drive Bridge Seismic Retrofit project involves the retrofitting of the existing bridge on Avila Beach Drive over San Luis Obispo Creek. The project aims to increase the bridge's strength to prevent collapse during an earthquake. The contract was awarded to Souza Engineering Contracting, Inc. and Granite Construction Company. The project includes various tasks such as temporary stream diversion, construction area signs, traffic control system, and structural concrete work. The contract has a total bid amount of $1,757,316.50 for Souza Engineering Contracting, Inc. and $2,789,237.00 for Granite Construction Company.
• The project involves seismic retrofitting of the Avila Beach Drive Bridge.
• The contract was awarded to two vendors: Souza Engineering Contracting, Inc. and Granite Construction Company.
• The project includes various tasks such as temporary stream diversion, construction area signs, and structural concrete work.
• The contract has a total bid amount of $1,757,316.50 for Souza Engineering Contracting, Inc. and $2,789,237.00 for Granite Construction Company.
• The project manager is Matt Reinhart, and the project engineer is Drake Haglan.
• The point of contact for this contract is JR Beard.