The Inglewood Hill Lift Station Odor Abatement Project involves the supply, installation, and commissioning of a new fan and biofilter odor control system, as well as the demolition of the existing odor control vessel. The project includes various tasks such as constructing a concrete structure, installing a water cabinet, and performing electrical work. The project's estimated value is around $190,000. The successful bidder, Westerlund Excavation, was awarded the contract with a total bid amount of $187,245.
• The project requires the installation of a new 1,200 cubic feet per minute (cfm) FRP exhaust fan and 5 HP motor.
• The existing biofilter and base outside the building will be demolished and removed.
• A concrete structure will be constructed to house an air distribution plenum and 5 ft depth organic media.
• A water cabinet with humidification and irrigation control components will be installed.
• The project includes various other tasks such as installing humidification and irrigation piping, performing electrical work, and commissioning the system.