This contract calls for the complete nuisance‑abatement demolition of a wood‑framed structure located at 801 ½ Kentucky Street, including removal of concrete footings, utility caps, debris, vegetation, and site stabilization. The work must be performed as a wet demolition to control lead‑based paint and asbestos, with strict erosion‑control BMPs and post‑demolition site seeding. The contractor must also publish a final‑completion notice in a local newspaper and provide extensive close‑out documentation (AIA forms, insurance certificates, E‑Verify proof). The solicitation was a sealed‑envelope RFQ with a submission deadline of August 24 2022, and the award was made to DEESE LAWN CARE.
• Scope: wet demolition, utility capping, debris removal, erosion‑control, hazardous‑material handling, site stabilization.
• Administrative requirements: E‑Verify enrollment, city business license, insurance, AIA payment and lien releases, newspaper notice.
• Timeline pressures: work must be completed within 15 calendar days after notice to proceed, with $250/day liquidated‑damage for delays.