The 114 E Wilson Site Restoration project is a municipal public‑works contract to restore a former parking‑ramp lot in downtown Madison. The scope includes demolition, grading, installation of a 4‑inch perforated under‑drain, placement of topsoil, erosion‑control matting, terrace seeding, construction of a cast‑in‑place concrete retaining wall, and installation of a 5‑ft ornamental steel fence with a swing gate. Traffic‑control planning, utility coordination, and compliance with OSHA and city specifications are required. The contract is a lump‑sum award to Speedway Sand & Gravel, Inc. for $167,390.77, with work scheduled to begin 27 Mar 2026 and be completed by 15 May 2026.
• Site grading, drainage, and erosion‑control (topsoil, matting, seeding).
• Concrete retaining wall and ornamental fence construction.
• Required traffic‑control, utility verification, and safety compliance.
• Single‑vendor, best‑value award with a Small‑Business‑Enterprise participation goal.