This contract concerns the rapid, wet‑demolition of an existing wood‑framed structure located at 960 Bernice Hudson Drive in Mobile, Alabama, together with comprehensive site remediation. The contractor must cap and certify utility lines, remove all debris—including tires, vegetation, and small trees—implement erosion and sediment controls, comply with lead‑based paint and asbestos disposal requirements, and provide final site stabilization. The award follows a sealed‑envelope RFQ with a 15‑day performance window and includes strict documentation, insurance, and lien‑release obligations.
• Wet demolition with hazardous‑material (LBP/ACM) handling and disposal at permitted landfills
• Full utility termination, capping, and certification (sewer, water, gas)
• Mandatory erosion‑control BMPs, temporary silt fencing, permanent seeding/mulching, and post‑completion photographic documentation
• Contractor must submit notarized payment applications, E‑Verify proof, insurance certificates, and a newspaper “Notice of Final Completion”
• Liquidated damages of $250 per day apply if work exceeds the 15‑day completion deadline