This contract is for the 3735 Tunnel Repairs Phase VI-B project, which involves the removal and replacement of underground concrete utility tunnel walls and lids. The project has a total bid value of $648,432.00, and the awarded vendor is LC Structural. The project is expected to be completed within 150 calendar days from the notice to proceed. The contract includes provisions for subcontractors, wage rates, and compliance with New Mexico state laws and regulations.
• The project requires the removal and replacement of 197.23 LF underground concrete utility tunnel walls and lids.
• The project has a total bid value of $648,432.00.
• The awarded vendor is LC Structural.
• The project is expected to be completed within 150 calendar days from the notice to proceed.
• The contract includes provisions for subcontractors, wage rates, and compliance with New Mexico state laws and regulations.