This contract concerns the interior renovation of the McHenry County Coroner’s Offices and associated autopsy rooms in Woodstock, Illinois. The scope includes demolition, concrete work, masonry, metal framing, insulation, drywall, flooring, finishes, casework, mechanical, electrical, plumbing, fire‑suppression, and related commissioning activities, all performed under an AIA A201 (2017) general‑conditions framework. The award was given to Stuckey Construction on a firm‑fixed‑price basis, with a base‑bid of approximately $750,000 and an additional $40,000 allowance for overhead, profit, and bonding. The project must commence no earlier than August 4 2025 and achieve substantial completion by December 15 2025. Key points include:
• Full‑service interior renovation of forensic/medical facilities, requiring compliance with OSHA, NFPA, and Illinois prevailing‑wage statutes.
• Single‑prime‑contract award to Stuckey Construction; all bids were submitted electronically with a 9:00 AM CST deadline on January 29 2025.
• Mandatory bid bond of 10 % of the bid amount and performance/payment bonds of 110 % of the contract sum.