The Ballenger McKinney Waste Water Treatment Plant Sludge Management Plan contract is for the update of the sewerage flow projections to the Ballenger McKinney Wastewater Treatment Facility and the estimation of when the influent flows would exceed 10 MGD. The contract also includes the review and re-evaluation of the previously proposed sludge management assumptions, the review and update of the 2006 Facility Plan for the location of the proposed Phase 1 & 2 sludge management facilities, and the preparation of a Preliminary Engineering Report to define the recommended sludge management facility.
• The contract was awarded to Whitman, Requardt & Associates, LLP.
• The bid posting date was July 12, 2022, and the bid submission date was August 17, 2022.
• The contract is for the provision of professional services related to the sludge management plan.
• The contract includes the update of the sewerage flow projections and the estimation of when the influent flows would exceed 10 MGD.
• The contract also includes the review and re-evaluation of the previously proposed sludge management assumptions and the review and update of the 2006 Facility Plan.