The City of Spokane Wastewater Maintenance department issued RFQ 5514‑21 to procure 828 feet of 8‑inch ductile‑iron pipe for its wastewater system. After an open competition, the contract was awarded to HD Fowler Company, which submitted the lowest‑priced quote. The tabulation shows three pricing alternatives, the highest total (including 9 % sales tax) being $28,086.42 and the lowest $21,750.73, with lead‑times ranging from 5 to 30 business days ARO. The solicitation included standard terms and conditions covering warranties, delivery, and inter‑local purchase provisions.
• Scope: Supply of 828 ft of 8‑in. ductile‑iron pipe (consolidated supply).
• Vendor: HD Fowler Company (sole awardee).
• Value: Approx. $21‑$28 k depending on selected pricing option.
• Lead‑time: 5–30 business days after receipt of order.
• Award date: 23 Sept 2021; contract is a one‑time purchase with no renewal language.