The City of Johnson City is refurbishing the interior flooring of Freedom Hall Civic Center with an epoxy‑based decorative flake system. The work includes removing existing paint/epoxy, repairing concrete, and scuffing porcelain tile in restrooms to ensure proper adhesion. The contract is a small‑scale municipal flooring project valued at roughly $25 k, with a tight schedule that must avoid scheduled arena events.
• Scope: 1,152 sf of stair hallways, 680 sf men’s restroom, 1,033 sf women’s restroom – removal, concrete repair, and epoxy‑flake coating.
• Schedule: Work to be performed between Jan 11‑14 2026 (hallways) and Jan 18‑22 or Feb 5‑10 2026 (restrooms), completed by Feb 28 2026.
• Requirements: Vendor must provide full labor/materials, a minimum 1‑year warranty, 5‑year commercial warranty for hallways, and submit extensive insurance, licensing, and drug‑free workplace documentation.