This contract concerns the wet demolition and complete site remediation of a vacant structure located at 7272 14th Street, Mobile, AL. The contractor must remove all building components, cap utilities, control erosion, dispose of lead‑based paint and asbestos, and restore the site with grading, topsoil, seed, and mulch. All work must be completed within 15 days of receiving a Notice to Proceed, with liquidated damages for any delay. The scope includes securing permits, providing insurance, and publishing a final notice of completion.
• Wet demolition of all structures, footings, and debris removal.
• Utility disconnection, capping, and compliance with local utility agencies.
• Environmental controls: erosion/sediment BMPs, lead‑asbestos handling, and post‑demolition site seeding.