This contract calls for the wet‑demolition and removal of all structures located at 2859 Ralston Road, Mobile, AL, including utility caps, debris clearing, erosion control, and site restoration. The City of Mobile’s Municipal Enforcement Department issued a Request for Quote (RFQ) with a stipulated‑sum “lump‑sum” format, required E‑Verify enrollment, insurance, and a rapid post‑award schedule (NTP within 3 business days, 30‑day work window). The successful vendor, L & L HAULING LLC, must deliver all demolition, waste disposal (including lead‑based paint/asbestos handling), temporary BMPs, permanent site stabilization, seeding, and close‑out documentation, with liquidated‑damage penalties for delays.
• Wet demolition of structures, footings, slabs, and piers with full debris removal.
• Utility disconnection and capping (sanitary sewer, water, gas).
• Erosion‑control BMPs, lead‑based paint/asbestos handling, and post‑demolition seeding.
• Strict timelines: quote deadline July 17 2024, NTP‑to‑completion within 30 days, $250/day liquidated‑damage after 15 days past substantial completion.