The Utah Division of Facilities Construction and Management (DFCM) is requesting bids for the construction of two new unisex bathrooms on level one for the public and one new unisex restroom on level two for the public at the Matheson Courts in Salt Lake City, Utah. The construction cost estimate is $200,000.00, and the completion date is November 1, 2024. The contract was awarded to Commercial Service Contractors, Inc. and Rod Lewis Construction, LLC. Key points of contact include Mike Raffael, Kasey Malan, and Rod Lewis.
• The project consists of creating two new unisex bathrooms on level one for the public and one new unisex restroom on level two for the public.
• The construction cost estimate is $200,000.00.
• The completion date is November 1, 2024.
• A mandatory pre-bid meeting and site visit were held at 9:30 AM on Tuesday, July 16, 2024.
• The bid documents were available at 3:00 PM on Monday, July 8, 2024, on the Utah Public Procurement Place (U3P) website.