This sealed‑bid contract awards the City of Worcester’s Sewer Rehabilitation (S25‑2) project to National Water Main Cleaning Company. The work includes cured‑in‑place pipe (CIPP) installation, manhole rehabilitation (epoxy and cementitious lining), sewer cleaning, TV inspection, service‑connection repair, and provision of a temporary bypass pumping system across several streets (Everett Gaylord Blvd, Laurel St, Summer St). The contractor must meet strict performance and payment bond requirements, adhere to prevailing‑wage schedules, submit weekly certified payroll, and complete the entire scope within 90 calendar days from contract execution.
• Install ~862 LF of structural CIPP pipe and rehabilitate 58 VF of manholes.
• Provide temporary bypass pumping, rodent control, dust/traffic control, and environmental safeguards.
• All work must be performed under a 5 % bid security, with 10 % retainage on major items, and documented via TV logs, videos, and hard‑drive deliverables.