Description
The Rock Creek Transmission Main Replacement Project involves the replacement of the existing transmission main with a new HDPE pipe. The project includes yard piping, control valve vault, electrical and instrumentation at the Rock Creek Water Treatment Plant, as well as 8700 feet of HDPE pipe along Rock Creek Road and Henkle Way public rights of ways. The project also includes erosion and sediment control. The bid tabulation summary lists the companies that submitted bids, along with their corresponding costs. The companies are North Santiam Paving, Lawson Corp, Pacific Excavation, Inc, Emery & Sons Construction Group, LLC, and J.W. Fowler. The bid costs range from $6,947,412.50 to $9,233,090.00.
• The project involves the replacement of the existing transmission main with a new HDPE pipe.
• The project includes yard piping, control valve vault, electrical and instrumentation at the Rock Creek Water Treatment Plant.
• The project includes 8700 feet of HDPE pipe along Rock Creek Road and Henkle Way public rights of ways.
• The project includes erosion and sediment control.
• The bid tabulation summary lists the companies that submitted bids, along with their corresponding costs.