This contract concerns the procurement and installation of a single 400 hp vertical turbine motor for Water Production Well 32 owned by the City of Dothan Utilities. After an open competitive bidding process, the award was recommended to Integrated Power Services – Dothan Electric for a GE‑manufactured motor priced at $35,025.70. The work is limited to supplying the motor and completing its installation on the specified well, with a lead‑time of approximately six weeks after award.
• Scope: Supply and install a 400 hp vertical turbine motor for a municipal water well.
• Awarded Vendor: Integrated Power Services – Dothan Electric (price $35,025.70).
• Procurement Method: Full and open competition with multiple bidders, single‑award decision.
• Timeline: Bid opening 3/10/2026, award resolution 3/24/2026; vendor to deliver within six weeks.
• Funding: Approximate contract value under $40 k, funded by City of Dothan Utilities.