This contract calls for the wet demolition of all structures at 2813 Berkley Avenue, including removal of footings, slabs, masonry, debris, and utilities, with stringent environmental controls for erosion, lead‑based paint, and asbestos. The City of Mobile Municipal Enforcement Department issued an RFQ (ME‑088‑23) and awarded the work to LTS Development Group. The contractor must begin after a formal Notice to Proceed and finish within 15 calendar days, with liquidated damages of $250 per day for overruns. Post‑award responsibilities include E‑Verify proof, insurance, schedule of values, final publication notice, and detailed close‑out documentation.
• Wet demolition of residential/commercial structures plus utility capping.
• Mandatory erosion‑control BMPs and hazardous‑material handling (lead, asbestos).
• Tight performance window (15 days) and $250/day liquidated‑damage clause.