This contract calls for the wet demolition of existing structures at 2451 McArthur Avenue, including removal of concrete block/brick frames, slabs, footings, utilities, and site clearing, followed by erosion‑control BMPs, proper disposal of lead‑based paint and asbestos, and final site stabilization with seeding. The contractor must submit E‑Verify proof, insurance certificates, and a stipulated‑sum agreement within two days of award, begin work within three business days of a Notice to Proceed, and complete all work and documentation within thirty calendar days. Liquidated damages of $250 per day apply for delays beyond substantial completion. The City of Mobile’s Municipal Enforcement Department oversees the procurement, with Gary Jackson as the primary contact.