Baldwin Contracting Company, Inc. dba Knife River Construction
Description
The City of Chico has awarded a contract for the construction of a roundabout intersection at Eaton Road and Floral Avenue. The contract was awarded to Baldwin Contracting Company, Inc. dba Knife River Construction in the amount of $2,998,182.35. The project involves the construction of a roundabout, including new pavement, curb and gutter, sidewalk, retaining walls, landscaping, lighting, and signing and striping. The contract has a duration of 180 working days and is funded by local funds. The contractor is required to pay prevailing wage rates to workers and to comply with state contract nondiscrimination and compliance requirements.
• The contract includes the construction of a roundabout intersection
• The project involves new pavement, curb and gutter, sidewalk, retaining walls, landscaping, lighting, and signing and striping
• The contract has a duration of 180 working days
• The contractor is required to pay prevailing wage rates to workers
• The contract is funded by local funds
• The contractor must comply with state contract nondiscrimination and compliance requirements