Awarded vendors
- Nu Vision Construction, Inc.
Description
This contract calls for the emergency demolition of a structure located at 1456 St. Stephens Road, Mobile, AL. The City of Mobile’s Municipal Enforcement Department required a wet‑demolition method, full utility capping, complete site clearing, and comprehensive erosion‑and‑sediment control, including BMP installation and final site stabilization. The contractor must also manage lead‑based paint and asbestos disposal, provide detailed documentation (photos, waste‑shipment records, close‑out affidavits), and publish a final‑completion notice in a local newspaper. The work must be completed within 15 calendar days of receiving a Notice to Proceed, with a $250 per day late‑work penalty thereafter.