This contract concerns the full rehabilitation of the Warrensville Center Road (CR‑4) between Fairmount Boulevard and Mayfield Road in the cities of University Heights and South Euclid, Ohio. The project is a high‑profile roadway reconstruction with an estimated construction budget of $7.7 million and an awarded amount of approximately $6.22 million. Bids were accepted through the Cuyahoga County Supplier Portal and in‑person, with a submission deadline of 2 PM on January 21 2026. The work must be completed no later than June 18 2027, and only ODOT‑pre‑qualified contractors are eligible to submit bids. The agency overseeing the procurement is Cuyahoga County’s Department of Purchasing, and the primary contacts are Purchase Analysts William Boyd and Andrew Johnson.
• Scope: Full roadway rehabilitation (including paving, sub‑grade work, drainage, and related civil works).
• Estimated Cost: $7,700,000; Awarded Value: $6,224,147.
• Key Dates: Bid opening Jan 21 2026; Project completion deadline Jun 18 2027.