The 2024 Road Rehabilitation Project involves the removal of existing striping, sweeping roads, patching of recessed marker depressions, application of Type II Micro-surfacing, installation of chip-seal, restriping, and installation of new recessed markers. The project is expected to begin at the end of June 2024 and be completed in 40 working days. The contract was awarded to VSS International as the lowest responsive, responsible bidder.
• The project consists of three main areas: Cascade Shores, Mountain Lake Estates, and Long Valley Road.
• The project requires the installation of county-provided project signs, placement of CMS boards for public notification, and removal of existing striping.
• The project involves the application of micro-surfacing, double chip seal, and new recessed markers.
• The Engineer's Estimate for the project is $1,355,000.
• The contract was awarded to VSS International for a total bid amount of $1,340,120.00.