This contract calls for the wet demolition of all structures at 357 Rylands Lane, Mobile, AL, including utility termination, debris removal, erosion‑control BMP installation, hazardous‑material handling, and site restoration. The City of Mobile’s Municipal Enforcement Department issued an RFQ on June 8 2023, received sealed quotes by June 14 2023, and subsequently awarded the job to CDI Investment Enterprise, Inc. The contractor must complete the work within 15 calendar days of receiving a written Notice to Proceed; any delay beyond this period incurs a $250 per day liquidated‑damage penalty. Extensive close‑out documentation (AIA forms, insurance certificates, E‑Verify proof, after‑action photos, waste‑shipment records, and a published notice of final completion) is required.