The contract is for the Troutman Boulevard Roadway Improvements project, which includes the full depth reclamation and paving of a 2-lane divided road approximately 1.25 miles long. The contractor will be responsible for testing the in situ road base material, having an engineer determine the proper additive and rate of application, and performing compaction, final grading, and bituminous prime. The contract was awarded to Florida Highway Products Inc. for the amount of $849,799.57. Some key features of the project include:
• Full depth reclamation and paving of the roadway
• Testing and analysis of the road base material
• Compaction, final grading, and bituminous prime
• Installation of a 2-foot strip of sod adjacent to the edge of pavement
• Maintenance of traffic patterns throughout construction
• Restoration of all disturbed areas