This contract involves the wet‑method demolition of all structures at 5910 Westhaven Drive South, Mobile, AL, including footings, slabs, utility disconnection and capping, debris removal, erosion‑ and sediment‑control, and post‑demolition site stabilization. The work must comply with lead‑based paint and asbestos handling requirements, include full documentation (photos, waste‑shipment records, close‑out forms), and be completed within a tight 30‑day window after the notice‑to‑proceed. The City of Mobile’s Municipal Enforcement Department issued a sealed‑bid RFQ (ME‑032‑24) with a bid deadline of 23 Oct 2024; the award was made to CFR SERVICES LLC. Key points:
• Wet‑method demolition with hazardous‑material (LBP/ACM) compliance.
• Full erosion‑ and sediment‑control BMPs required, plus final seeding/mulching.
• Contractor must obtain all permits, hold a City business license, and be enrolled in E‑Verify.
• Stipulated‑sum payment with potential $250/day liquidated‑damage for late substantial completion.