The contract is for the 108th Ave NE and NE 4th St Intersection Improvements project, with a total engineer's estimate of $639,767. The project involves various tasks such as removing structures and obstructions, constructing cement concrete curb and gutter, and storm drainage improvements. The contract was awarded to two vendors: Kamins Construction and Road Construction Northwest, Inc. The bid prices for these vendors are $517,816.12 and $673,089.15, respectively.
• The project requires the removal of structures and obstructions
• The project involves the construction of cement concrete curb and gutter
• The project includes storm drainage improvements
• The project requires property restoration and miscellaneous work
• The project involves the reconfiguration of planter strips
• The project requires the revision of storm pipe and catch basin layout
• The project includes signal and illumination modifications