The City and Borough of Wrangell awarded a municipal roof‑replacement contract for its Community Center. The project required complete demolition of the existing metal roof, removal of a chimney, installation of a new standing‑seam metal roof system, self‑adhering underlayment, ice‑and‑water shield, insulation, gutters, and associated flashing. Johnson Construction & Supply, Inc. was the low‑bidder and assumed responsibility for all demolition, material procurement, installation, and close‑out documentation. The contract was a fixed‑price, single‑prime award with a base‑bid estimate of approximately $330,000 and a final awarded price of roughly $306,800. Key milestones included a pre‑bid conference on May 24 2012, bid submission deadline June 4 2012, substantial completion by October 15 2012, and final completion by November 30 2012. The procurement followed an open competitive process with a $25 document fee and standard municipal bonding and insurance requirements.
• Scope: full roof removal, chimney demolition, installation of new metal roofing, insulation, gutters, and flashings.
• Awardee: Johnson Construction & Supply, Inc. (Alaska contractor).
• Timeline: May 23 2012 start → November 30 2012 final completion (≈6 months).
• Value: Engineer’s estimate ≈ $330 k; awarded bid ≈ $307 k.
• Procurement: Open competition, sealed bids, 5 % bid bond, performance and payment bonds required.