This contract calls for the complete wet demolition and removal of all structures, footings, slabs, utilities, and debris at 1001 Barbara Drive E, Mobile, AL, followed by erosion‑ and sediment‑control BMPs, lead‑based‑paint/asbestos handling, site‑stabilization, and post‑demolition documentation. The City of Mobile’s Municipal Enforcement Department issued a sealed‑envelope RFQ (ME‑111‑21) on April 19 2022, with quotes due by 2 PM on April 25 2022. The awarded vendor, AA&A Demolition, must complete the work within 15 calendar days after receiving a written Notice to Proceed and will be subject to a $250 per day liquidated‑damage penalty for any overruns. Required close‑out items include final photographs, waste‑shipment records, a newspaper notice of final completion, and AIA lien‑release affidavits. The procurement was a full and open competition, stipulating a single lump‑sum price.
• Wet demolition of all structures, utilities, and vegetation, retaining the existing aluminum fence.
• Mandatory erosion, sediment, lead‑paint, and asbestos BMPs with daily inspections and final site‑stabilization (seeding/mulching).
• Tight performance schedule – 15 days to achieve substantial completion, with $250/day liquidated‑damage penalty.