The contract is for concrete sidewalk repair at the BC Justice Center in Hackensack, New Jersey. The project involves furnishing all labor, materials, tools, equipment, and insurance required by the contract documents. The total bid for the project is $57,250. The contract has a duration of 365 days and is set to expire on December 12, 2024. The vendor, AA Berms LLC, has proposed to complete the work in 10 calendar days. Key aspects of the project include:
• Concrete flatwork: $43,500
• General conditions: $13,750
• Total bid: $57,250
The contract is subject to renewal after the end date.