This contract is for the replacement of flooring in Building E at Topeka West High School. The contract includes a base bid for LVT - Type 1 flooring in the classrooms, as well as add alternate bids for LVT - Type 1 flooring in the staff workroom and storage area, and for CS - Type 1 flooring in the office suites and corridor. The contract also includes an allowance for field changes and a unit cost for additional concrete repairs. The total awarded bid is $50,375.00.
• The contract is for a lump sum payment.
• The contract includes a 10-day work period for Fox Ceramic Tile and an 8-day work period for JP Construction LLC.
• The contract has a lead time of 2-3 weeks for Fox Ceramic Tile and 5 weeks for JP Construction LLC.
• The contract includes a $10,000 allowance for field changes.
• The contract includes a unit cost of $2.50 per square foot for additional concrete repairs.