The Pavement Rehabilitation Project - Burns Drive is a construction project that involves the replacement of asphalt pavement and repair of curb and gutter as necessary. The project was awarded to multiple vendors, including J&J Asphalt Company, Hills Materials Company, Knife River-Rapid City, and Simon Contractors of SD, Inc. The engineer's estimate for the project was $100,000.00, and the base bids from the vendors ranged from $180,460.25 to $291,014.90. The project is part of the City of Rapid City's capital improvement program.
• The project involves the replacement of asphalt pavement and repair of curb and gutter as necessary.
• The project was awarded to multiple vendors, including J&J Asphalt Company, Hills Materials Company, Knife River-Rapid City, and Simon Contractors of SD, Inc.
• The engineer's estimate for the project was $100,000.00.
• The base bids from the vendors ranged from $180,460.25 to $291,014.90.