The City of Roseville's Roller Compacted Concrete Pilot Project involves constructing roller compacted concrete pavement at various locations. The project includes portland cement concrete pavement, hot mix asphalt, concrete curb and gutter, aggregate base, cement treated base, roadway excavation, diamond grind concrete pavement, drainage system, concrete retaining wall, traffic striping, traffic signal modification, ADA ramps, and other items. The bid deadline was January 17, 2017, and the bid opening was on the same day. The engineer's estimate for the project is $6.7 million.
• The project requires registration with the Department of Industrial Relations (DIR) before bidding on public works contracts in California.
• The project includes various documents, such as the RCC Pilot Project Manual, plan sets, and addendums.
• The bid bond is required, and the bidders must provide a superintendent's resume and other documents.
• The project has a total of 17 questions and 14 new answers.