The contract is for the replacement of the #3 compressor on the City-County Building Roof Chiller. The winning bidder, Powell Mechanical, Inc., will provide labor, equipment, materials, and supplies for the project. The contract period is 90 days from the effective date of the Notice to Proceed, which will be issued between August 1, 2017, and December 31, 2017. The estimated cost of the project is $46,500.00.
• The contract was awarded to the lowest responsive and responsible bidder.
• The project is part of the county's capital budget.
• The contract includes a notice to proceed, which will be issued between August 1, 2017, and December 31, 2017.
• The contract period is 90 days from the effective date of the notice to proceed.
• The estimated cost of the project is $46,500.00.