The contract is for the replacement and retrofit of roll-up doors at the Central Branch Library. The contract was awarded to Dorothybuilds.com, and the project is expected to be completed by October 16, 2023. The contract has a budget of $54,800. Key aspects of the contract include the replacement of doors, frames, and jambs, as well as the installation of new door operators and hardware. The contract also includes the removal and disposal of existing doors and materials.
• The contract is a construction contract, and the work will be performed at the Central Branch Library.
• The contract has a duration of 119 days, and the project is expected to be completed by October 16, 2023.
• The contract has a budget of $54,800, and the payment terms are not specified in the document.
• The contract includes the replacement of doors, frames, and jambs, as well as the installation of new door operators and hardware.
• The contract also includes the removal and disposal of existing doors and materials.