This contract calls for the demolition of two existing red‑brick restroom facilities at Lake Afton Park and the construction of two new, site‑built masonry restroom buildings (West and East). The work is a lump‑sum, firm‑fixed‑price contract awarded to a single general contractor and includes all labor, materials, permits, insurance, and bonding required for public‑works construction. The scope encompasses demolition, new masonry walls, roof trusses engineered by a Kansas‑licensed structural engineer, new electrical service with TVSS, LED lighting, World‑Dryer hand dryers, bug‑screened louvers, interior poplar trim, and associated site work. No optional alternates (partitions, ceiling, tile) were awarded. The project is funded by Sedgwick County’s Project Services budget and was competitively bid by 155 vendors.
• Scope: Demolition + new construction of two identical restroom buildings (≈ 350 k each).
• Award: Conco, Inc. – $700,000 total base bid (no alternates).
• Schedule: Bid opening 5 Nov 2024; award approved 20 Nov 2024; completion timeline not disclosed but typical public‑works timelines range 4–9 months.