The contract is for hot mix asphalt paving services, with a cost estimate of $1,000,001 - $2,500,000. The project includes full depth reclamation of existing pavement, milling of existing pavement, placement of hot mix asphalt base and surface courses, construction of driveway tie-ins, filling of shoulder drop-offs, stabilization of disturbed areas, maintenance of traffic, and all incidental work as indicated in the specifications or special provisions. The contract was awarded to CJ Miller for $1,525,823.97.
• The project consists of various roadwork activities, including full depth reclamation and hot mix asphalt placement.
• The contract was awarded through a competitive bidding process, with the bid submission date being June 14, 2017.
• The contract award date was July 26, 2017.
• The contract details, including the award amount and vendor information, are provided in the CONTRACT AWARD section.