The contract is for the Newcastle Sewer System Repairs 2021 project, which involves repairs to the existing sewer system. The work includes the installation of manholes, cleanouts, and sewer pipes, as well as the abandonment of certain pipes and the rerouting of laterals. The contract was bid on by several companies, with base bid amounts ranging from $123,580 to $158,250. The contract was likely awarded to the bidder with the lowest base bid amount.
• The project is divided into five projects.
• The work includes the installation of 7 manholes and 9 cleanouts.
• The work includes the replacement of approximately 10 feet of 6-inch sewer pipe.
• The work includes the abandonment of approximately 120 feet of 8-inch pipe and one manhole.
• The work includes the rerouting and reconnection of one lateral.