The contract is for the construction of a new salt storage building at the Euclid Creek Reservation, designed to replace the existing structure which is showing significant structural deterioration. The new building will be 22'x24' with a 8'tall concrete foundation wall and will have the capacity to store approximately 100 tons of salt. The contract was awarded to Alabasi Construction, Inc. for a lump sum of $65,000.00. Key features of the project include:
• Construction of a new salt storage building
• Replacement of the existing structure
• Capacity to store approximately 100 tons of salt
• 22'x24' building with 8'tall concrete foundation wall
• Framing, siding, roofing, and painting included in the scope of work