The contract is for foundation and site development at Blackstone Valley Regional Vocational Technical High School. The project includes cast-in-place concrete, sewer line replacement, and thermal and moisture protection. The contract was awarded to Peter Amorello Construction & Dem., Inc and Zeyco Construction LLC. The substantial completion date is August 11, 2025. Key aspects of the project include:
• Foundation work
• Site development
• Cast-in-place concrete
• Sewer line replacement
• Thermal and moisture protection
• Substantial completion by August 11, 2025