The 119th Street Arterial (K-7 Highway Interchange & Black Bob to Pflumm Road) 2017 Street Preservation Program is a construction project that involves the preservation of 119th Street in Olathe, Kansas. The project includes milling and asphaltic surface overlay, concrete joint repair, and other work. The contract was awarded to three vendors: Freeman Concrete Construction, LLC, O'Donnell & Sons Construction Co., and McAnany Construction Inc. The bid amounts for each vendor are listed, with Freeman Concrete Construction, LLC submitting the lowest bid of $1,603,335.55. The project is expected to be completed within a certain timeframe, although the exact duration is not specified.
• The project involves the preservation of 119th Street in Olathe, Kansas.
• The contract was awarded to three vendors: Freeman Concrete Construction, LLC, O'Donnell & Sons Construction Co., and McAnany Construction Inc.
• The bid amounts for each vendor are listed, with Freeman Concrete Construction, LLC submitting the lowest bid of $1,603,335.55.
• The project includes milling and asphaltic surface overlay, concrete joint repair, and other work.
• The City of Olathe, Kansas, is the agency responsible for the project.
• The project is expected to be completed within a certain timeframe, although the exact duration is not specified.