This contract awards the replacement of the Thermoplastic Polyolefin (TPO) roof on the main terminal of Appleton International Airport. The work involves full removal of the existing built‑up roof system, installation of a new TPO single‑ply membrane, associated insulation, vapor retarder, and new sheet‑metal flashings, all performed under a lump‑sum, stipulated‑price agreement. The project is funded by Outagamie County and will be carried out by Security Luebke Roofing under a schedule that begins after May 10 2024 and must reach substantial completion by October 31 2024, with liquidated damages of $500 per day for delays. Key contract provisions include a 5 % bid bond, performance and payment bonds equal to the contract sum, and extensive insurance requirements detailed in Attachment A.
• Scope: Full roof demolition, insulation, TPO membrane installation, and flashing work on a commercial airport terminal.
• Schedule: Work start ≥ May 10 2024; Substantial completion ≤ Oct 31 2024.
• Financials: Awarded bid $174,830; 5 % bid bond; performance/payment bonds equal to contract sum; $500/day liquidated damages.