The contract is for the installation of a temporary single-lane bridge over Arroyo Grande Creek to restore vehicular access via Cecchetti Road. The project includes provisions for traffic control, temporary pavement marking, and water pollution control. The contract was awarded to two vendors, Souza and R Burke Corporation, with a total base bid of $475,998 and $515,400, respectively. The contract also includes additive provisions for winter installation and removal. Key points to consider when evaluating this contract include:
• The contract is for a temporary bridge installation
• The project includes provisions for traffic control and water pollution control
• The contract was awarded to two vendors
• The contract includes additive provisions for winter installation and removal
• The total base bid for the contract is $475,998 and $515,400, respectively.