The contract is for Loop Road Repairs and Repaving at the Sweetwater campus of Texas State Technical College. The project includes roadway reconstruction, new base material, grading, compaction, prime, new hot mix, and striping, as well as seal coating and drainage structure improvements. The contract was awarded to Raydon, Inc, but due to budget issues, TSTC is not moving forward with the project. The proposed completion date was 8/2/2021, and the total bid was $828,637.20.
• The project includes roadway reconstruction and new base material
• The project includes grading, compaction, prime, new hot mix, and striping
• The project includes seal coating and drainage structure improvements
• The contract was awarded to Raydon, Inc
• The proposed completion date was 8/2/2021
• The total bid was $828,637.20