Description
The City of Leesburg invited bids for the Main Street Streetscape Project, which includes construction of the Main Street Streetscape, demolition, roadway construction, stormwater, concrete paving, brick paving, and other related work. The estimated construction budget is $2,110,000. The project requires a bid bond, and the awarded contractor must provide a performance bond and payment bond. The contract was awarded to Stage Door II, Inc. with a total base bid amount of $2,560,117.00. The project is expected to be completed within 191 days after the notice to proceed.
Key aspects of the project include:
• Construction of the Main Street Streetscape
• Demolition and roadway construction
• Stormwater management
• Concrete and brick paving
• Installation of traffic signals and site furnishings
• Landscaping and irrigation
The contract document includes a detailed bid tabulation, which lists the unit prices and extended costs for each item of work. The document also includes information on the bid submission process, the evaluation criteria, and the contract terms and conditions.