This contract calls for the wet‑demolition and complete site clearance of a vacant property at 1859 Jones Avenue in Mobile, AL, followed by erosion control, temporary and permanent stabilization, and reseeding of the cleared area. The contractor must cap and disconnect utilities, manage lead‑based paint and asbestos according to federal and state regulations, and provide extensive documentation, including before‑and‑after photographs, waste shipment records, and a published Notice of Final Completion. A $250 per day liquidated‑damage penalty applies if substantial completion is not achieved within 15 calendar days after the notice to proceed.
• Wet demolition of all structures, footings, slabs, and ancillary items; removal of debris and vegetation up to 8 in. diameter.
• Site restoration with erosion‑control measures, fill voids, and seed/mulch disturbed soils.
• Strict environmental compliance (NESHAP, Clean Water Act, local BMPs) and required post‑completion documentation.