The contract is for the repair of the Second Street Parking Ramp in Rochester, Minnesota. The work includes slab and column repairs, joint repairs, traffic coating and markings, painting, tuckpointing, waterproofing, replacement of the boiler system, light fixtures to LED, bollards, door and window repairs, and other preventive maintenance work. The contract was awarded to Paragon Restoration II, Inc. for $1,045,087.50. The project is expected to be completed by October 31, 2025.
• The contract is for a specific project with a clear scope of work
• The contract was awarded through a competitive bidding process
• The contractor is expected to complete the work by a specific deadline
• The contract includes provisions for prevailing wage, workforce goals, and targeted business initiatives
• The project is funded through the Parking Enterprise Fund, with a budget of $500,000 and additional funds to be covered by the unrestricted fund balance